Review of the additional/complementary works for the rehabilitation and upgrade of; Keya, Nkora and Cyimbili Mini Hydro Power Stations in Rubavu and Rutsiro District respectively.Scope of work:Situation analysis and assessment of damages of the plants and the works required to rehabilitate them to proper operational status.Reviewing all documents available (existing design studies, BOQs and contracts).Assessment and advisory on the proposed additional works and equipment required to increase productivity.Investigating whether the guaranteed production output of the plant can be realized. Establish possible measures that would be taken by EUCL (National Utility Company in Rwanda) in the event the plants are not able to meet the targeted production output as at Dec 2019. |